There was minimal movement in lead times despite some packages experiencing a change in enquiry levels and workloads
Rotary piling → lead times remain at seven weeks with no change anticipated over the next six months. Precast piling → lead times sit at four weeks with no change expected over the next six months. Concrete works → lead times stay at 10 weeks; contractors’ enquiry levels and workload are static, and lead times not set to change over the next six months. Structural steel frames → lead times have increased by two weeks to 17 weeks but no further variation predicted for the next six months as future order levels are unchanged.